Update – Electrical issue affecting subscribers – Redwood Valley / Potter Valley / Northern Ukiah

A generator was delivered to the affected site this morning and service was restored to all affected subscribers (that themselves have power) at 7:32AM. 

PGE’s current estimated time of grid power in the area is 2PM today. 

It was determined when on-site this morning that our backup battery bank has a failed battery, hence the short run-time of only ~2.5 hours.  I plan on replacing the battery bank this afternoon after grid power is restored.  The site will continue running on generator until that time.

Thanks,